Fictional case · Illustrative assumptions

From a disagreement
to a clear next step.

A contractor and employer disagree about additional work. Before choosing a route, bring the evidence, the questions and the commercial assumptions into one view.

01 / Establish what the records say

THE EVIDENCE

The contractor claims £160,000 for changes. The employer queries both the scope and the amount.

A recorded instruction

An email asks for a revised layout. The reference drawings and the authority for the change need confirming.

EX-01 / CORRESPONDENCE

A different valuation

The submitted valuation includes extra quantities. Some bill lines may already cover part of the work.

EX-02 / VALUATION

An incomplete daily record

The diary records work and resources. The link between the change and additional time is not yet established.

EX-03 / SITE DIARY

All records, amounts and references on this page are invented for the demonstration. The example follows the evidence and assumptions approach used in the existing Dispute Adviser Decision Studio.

02 / Separate findings from questions

THE ASSESSMENT
WHAT IS RECORDED

A change was discussed.

The example correspondence refers to a different layout. A claimed sum and supporting valuation have been submitted.

WHAT NEEDS TESTING

Scope, basis and amount.

Check the agreed baseline, the relevant instructions, the valuation method and any overlap with existing work.

WHAT CANNOT BE ASSUMED

Entitlement or outcome.

A document reference or a cost total does not decide liability. The contract, facts and contrary evidence still need professional review.

03 / Make the commercial assumptions visible

A CONDITIONAL COMPARISON

The figures below explore two assumed outcomes. They are not forecasts, fee quotations or recommended routes. Change them to see the arithmetic; no probability or legal conclusion is inferred.

Scenario A

Agreement after discussion

Payment less future costs£77,000

Scenario B

Further review and process

Payment less future costs£80,000

Scenario B is £3,000 higher on these inputs. Timing, recovery and outcome uncertainty are not priced here.

GBP, excluding VAT. Costs already incurred are omitted equally from both forward-looking scenarios. Interest, tax, enforcement, cost recovery, financing and non-cash objectives are excluded. An assumed payment is neither a probable recovery nor a settlement recommendation.

04 / Give the team a useful next step

THE REVIEW OUTPUT

Focused information request

Confirm the instruction and its drawing revision. Reconcile the disputed quantities against the original scope. Link resource records to the changed work.

A position that can be revisited

Record what supports the claim, what challenges it and what remains unknown. Update the options after the missing evidence and realistic route budgets have been reviewed.