ContractFlow / 5D planning
Cedar Court
See the building, programme and planned budget together.
Synthetic demonstration Six storeys · L-shaped block · 52-week programme
01 / Construction sequence
One model. Six cost packages.
Use the slider’s arrow keys to step through weeks. Home / End jump to start / finish.
03 / An inspectable basis
Illustrative inputs, visible calculations.
Every quantity, rate, drawing reference and programme window below was invented for this example. No supplier quotations or real project records are included.
| Package | Weeks | Quantity × rate | Budget |
|---|---|---|---|
| Groundworks | 0–8 | 2,400 m³ × £32 | £76,800 |
| Substructure | 6–14 | 520 m³ × £230 | £119,600 |
| Concrete frame | 12–32 | 680 m³ × £285 | £193,800 |
| Envelope | 24–40 | 2,200 m² × £145 | £319,000 |
| Building services | 30–46 | 2,280 m² × £78 | £177,840 |
| Internal fit-out | 36–52 | 2,280 m² × £110 | £250,800 |
| Whole-project planned budget | £1,137,840 | ||
Budget is spread evenly through each package’s stated window. Model stages show the same sequence at a schematic level; visible elements are not measured quantities. Services and fit-out are shown as floor markers. Stage completion follows the fictional programme, not observed site progress. Planned allocation is not actual expenditure, a payment forecast or earned value.
This simplified budget excludes VAT, fees, land, finance, contingency and explicit inflation. It is a demonstration, not a project estimate.